A cold bridge is an area through which increased loss of heat or cold occurs. It arises from the temperature difference between the inside and the outside of a building. When the air temperature outside the building is lower than inside, cold begins to travel from the cold area to the warm one through the structure. This leads to heat loss and condensation inside the building on the surface of the structure.

1.jpg

How to protect joints from cold bridges

At the joint of a wall and a roof sandwich panel, a cold bridge occurs when the metal facing of the roof panel is in both the warm zone and the cold zone at the same time. A cold bridge does not form through the insulation, so the metal must be interrupted zonally between the cold and the warm rooms.

To avoid a cold bridge at the installation stage, you need to interrupt the strip of metal running through from the room side to the outside. The metal facing can be interrupted by cutting off a small part of it across the entire width of the panel in the zone of the joint with the wall panel. It is the contact between the wall and roof insulation that ensures a closed thermal insulation loop around the building. This method is the fastest, simplest and most effective.

2.png

1 – Three-layer sandwich panel – PST              

2 – Metal frame structure

3 – Mounting foam

4 – Sealing tape

5 – Silicone sealant

6 – Self-tapping screw for sandwich panels

7 – Self-tapping screw for shaped elements

In addition, the joints must be filled with mounting foam, and the joints where shaped elements abut must be sealed with sealant to protect the inner layer from moisture and extend the service life of the structure.

3.png

Vertical corner joint with horizontal placement of sandwich panels in 3D

What to do if a cold bridge has already formed

It is advisable to apply preventive measures at the installation stage, since it is harder to eliminate freezing in a finished building. If you forgot to cut the metal before installation, a cold bridge may form on the surface of the metal facing sheet.

In this case you need to:

  • dismantle the sandwich panel
  • cut the metal on the side where condensation or ice forms
  • install the sandwich panels back
  • foam the joints with mounting foam
  • seal the joints where the shaped elements abut

Do not ignore the possibility of cold bridges; provide protection against them at the design stage to avoid additional costs in the future!

If you have questions during the installation of ProfHolod sandwich panels with PIR Premier or mineral wool, you can request advice from your personal manager at ProfHolod. You can also order supervised installation to be sure of the quality of the installation — ProfHolod specialists will come to the site to check that the sandwich panels are installed correctly and/or to supervise the work of the construction contractor.

Subscribe to updates of our knowledge base

And you will be the first to receive the latest recommendations from our engineers

More useful articles

We explain which characteristics of sandwich panels you should pay attention to in order not to make a mistake
10.12.2024
Can administrative buildings be built from sandwich panels with PIR Premier insulation
06.02.2024
Learn the important points of installing sandwich panels
02.02.2024
A balcony is insulated once – it is important to do it right the first time
13.09.2023

See our
projects

gototop